SNOQUALMIE VALLEY SCHOOL DISTRICT #410
2007 PROJECTS PLANNED - NEW CONSTRUCTION - REMODEL PROJECT - SITE ACQUISITION
Project Anticipated Source of Funds
               Student Capacity 
         State    Impact    Mitigation   For New Housing 
 Facility:   Location:   Capacity:   Bonds:   Match   Fees   Payments   Developments 
           
 Middle School #3  (46910 Middle Fork Road SE)   North Bend             600    2005/2008              -  2007/2008                   - YES
           
 Portable Classrooms (7-Bldgs,14-Rms)   Snoqualmie             378    2007/2008              -  2007/2008                   - YES
           
 Land for High School #2 (50 acres)   To Be Determined                 -    2007/2008              -  2007/2008                   - YES
           
 High School #2   To Be Determined          1,500    2007/2011 [1]             -  2007/2011                   - YES
           
 Elementary School #6   Snoqualmie Ridge             600    2007/2009              -  2007/2009                   - YES
           
 Elementary School #7   To Be Determined             600    2009/2011              -  2009/2011                   - YES
           
           
           
                 
          - Certified appraisals of land values, received by the District in October 2005, established the 2005 price of vacant land in the District at approximately 
            $297,000 per acre.  $297,000 per acre, without any consideration of inflation in land values for either 2006 or 2007, has been used as the cost per 
            acre of land in this plan 's impact fee calculations for High School #2.
            Also see notes at the bottom of page 12.
          - Middle School #3 will open in the Fall of 2008.
          - Current enrollment projections show the need for E.S. #6 in 2008, E.S. #7 in 2010, and additional H.S. Facilities in 2011.

[1]
Appropriate PROJECT COMPLETION CYCLE for
a  New 1,200 Student HIGH SCHOOL  FACILITY:
     - Planning the Facility(s)            =  One Year
     - Obtaining Voter Approval        =  One Year
     - Designing the Building(s)         =  One Year
     - Obtaining Necessary Permits  =  One Year
     - Constructing the Facility(s)     =  Two Years
==============================
Total Project Completion Cycle       = Six Years